Change Order (189 deliverables)
-
[700] 001_WABN Plant Establishment (PCO 015) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[701] 002_Apprentice Util Plan Submittal (PCO 032) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[702] 003_Foster Island Irrg Water Supp (PCO 028) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[703] 004_Amendment to Appendix (PCO 018, 019, 020, 021, 022, 025, 026, 040) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[704] 005_RSUP Cover Plates (PCO 001) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[705] 006_Tax Rule 170-171 Graham Bid Proposal Error (PCO 010) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[706] 007_Adjust Contract Dates (PCO 067) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[707] 008_CWA Amendment 1 (PCO 063) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[708] 009_MOT Signs and Safety Drums (PCO 069, 070) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[709] 010_WABS Girder Line (PCO 038) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[710] 011_Incentive Award Program Change (PCO 078) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[711] 012_Crosswalks (PCO 084) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[712] 013_ML Fire Supp & Ltg Mods (Nine PCO's) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[713] 014_TS Controller Submittal Sheet (PCO 072) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[714] 015_Added Engineering PDW 1 (PCO 007, 039, 087) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[715] 016_Stormwater Sampling (PCO 068) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[716] 017_Environmental Update 01 (PCO 027, 030, 073, 086) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[717] 018_Field Office Water and Sewer Connection (PCO 066) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[718] 019_Storefront (PCO 056) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[719] 020_CO Located Office Change (PCO 005, 057) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[720] 021_CCMP Extension Date (PCO 029) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[721] 022_Temporary Sidewalk Reduction (PCO 064) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[722] 023_Lake Wa Blvd Closure Hrs (PCO 052) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[723] 024_WABS Time Histories (PCO 082) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[724] 025_WABS Columns (PCO 093) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[725] 026_Hard Copies and Flash Drives (PCO 017) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[726] 027_Multiple Issue Resolution No. 1 (11 PCOs - See Log) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[727] 028_Digital Signatures (PCO 034) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[728] 029_Adjust Insurance Language Chapter 1 (PCO 004) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[729] 030_Baebler and Giordano TCEs (PCO 096) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[730] 031_Cell Tower ITS Conflict (PCO 091) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[731] 032_Sign Height (PCO 111) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[732] 033_DXEI Ramp HOV Lane Closure (PCO 105) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[733] 034_Force Account Markup Change (PCO 112) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[734] 035_Electrical Conduits on Girders (PCO 117) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[735] 036_COS Interconnect on Montlake (PCO 042) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[736] 037_North Street Closure (PCO 104) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[737] 038_Addl Existing Bridge As-Builts (PCO 132) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[738] 039_ATC 001 Adjustments (PCO 125) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[739] 040_Steel Casing for 54 in. Waterline (PCO 130) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[740] 041_WABN Settlement Monitoring (PCO 119) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[741] 042_Interpretive Signs (VOIDED)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[742] 043_Guardrail on MR Line (PCO 122) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[743] 044R1_Interpretive Signs-Bus Shelters (PCO 071, 137) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[744] 045_Maturity Meters (PCO 148) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[745] 046_ML Early Use-PBB Conn Trail (PCO 076, 080) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[746] 047_76 Gas Station Debranding (PCO 126) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[747] 048_Radiographic & Mag. Part. Insp (PCO 129) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[748] 049_Conduit Re-routing (PCO 159) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[749] 050_E-Signature Change Orders (PCO 177) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[750] 051_COS Signal Pole Finishes (PCO 106) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[751] 052_Montlake Temp Market Space (PCO 077) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[752] 053_Transite in Barrier Brg Struc (PCO 134) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[753] 054_Shaft Centralizer (PCO 171) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[754] 055_54 in. Waterline North Vault (PCO 102) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[755] 056_Permeable Conc-Col Trees Impact (PCO 131, 141) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[756] 057_Luminaire Mounting WDX Tunnel (PCO 149) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[757] 058_Flexible Conduit in Pier 2 (PCO 146) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[758] 059_COVID Pre-Suspension (PCO 150) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[759] 060_COVID Closeout Certification (PCO 186) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[760] 061_NOAA Property Modifications (PCO 059) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[761] 062_LWB Pvmt Mod-Resurf. LWB & Rke (PCO 180, 192) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[762] 063_Powder Coating Materials (PCO 184) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[763] 064_COVID Suspension of Work (PCO 154) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[764] 065_Fiber Conduit-Cable Revisions (PCO 172) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[765] 066_CWA Amendment 2 (PCO 201) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[766] 067_As-Built WDs-PE Encasement (PCO 152) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[767] 068_COVID Monthly Costs for Sanit (PCO 157) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[768] 069_Roanoke Plz Re-design Pricing (PCO 203) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[769] 070_UL Ltg Nighttime Cir - Design (PCO 187) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[770] 071_ATM Sign Controllers (PCO 162) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[771] 072_PLB Structure Requirements (PCO 044) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[772] 073_PE Encase for WSDOT DI Pipe (PCO 193) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[773] 074_Reinf. Steel Working Drawings (PCO 151) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[774] 075_FB&L Fire Hydrant Clar (PCO 196) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[775] 076_Demo of Ex. Seismic Retrofit (PCO 135) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[776] 077_COVID Completion of Work (PCO 165, 190) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[777] 078_EPS Bearing (PCO 043) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[778] 079_TMS Workstation Modifications (PCO 208) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[779] 080_CAD Conformance for RFC Docs (PCO 217) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[780] 081_Uninterruptible Power Supply (PCO 169) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[781] 082_Shotcrete at RSUP Tunnel (PCO 206) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[782] 083_CSL Testing Spec Modification (PCO 221) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[783] 084_COS Cut-In Signal Loops (PCO 108) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[784] 085_Incr Cond Size at St Crossings (PCO 204) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[785] 086_Sign Brdg Repair Wknd Closure (PCO 140) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[786] 087_24th Ave Signal Ctrl Cab Parts (PCO 166) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[787] 088_SPR Lighting Service Cabinet (PCO 189) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[788] 089_LED Underlid Ltg Spare Parts (PCO 051) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[789] 090_Roanoke Plaza Re-Design Work (PCO 224) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[790] 091_Barge Requirements (PCO 232) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[791] 092_Staging Area Modification (PCO 234) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[792] 093_Remove 6 Vib Monitors on WABN (PCO 231) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[793] 094_SR 520-6A Bent 2 Demo Changes (PCO 124) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[794] 095_Signage for Flammable Cargo (PCO 222) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[795] 096_WSDOT Sign Changes (PCO 114) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[796] 097_Montlake South Const Limits (PCO 216) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[797] 098_WABS Column Core Mix Design (PCO 235) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[798] 099_SIP Forms for Tub Girders (PCO 223) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[799] 100_ML Plaza Maintenance Access (PCO 179) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[800] 101_Maint Veh Turnaround on RSUP (PCO 197) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[801] 102_Pavement Section on Maint Path (PCO 198) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[802] 103_Dowels in SW's at Lid Edges (PCO 207) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[803] 104_COVID - Sanitation Extension (PCO 236) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[804] 105_Peninsula Gate Requirements (PCO 109) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[805] 106_Elim Brdg Drg Pipe Paint Rqmt (PCO 138) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[806] 107_RSUP Tunnel Lighting (PCO 183) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[807] 108_Seattle Design Comm Workshop (PCO 209) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[808] 109_Fdn & Conduit for Fut PBB Ramp (PCO 211) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[809] 110_Temp DWXI On-Ramp at NOAA Prop (PCO 215) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[810] 111_SPU 54-inch TM Shutdown Mods (PCO 212) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[811] 112_SDOT Chan Changes on E ML PL E (PCO 239) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[812] 113_SPU PRV Conn - Design Only (PCO 173) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[813] 114_Add'l Interpretive Signage (PCO 229) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[814] 115_Elimination of CO 95 Work (PCO 247) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[815] 116_Centurylink Agreement (PCO 243) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[816] 117_Lane Closure Modifications (PCO 249) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[817] 118_FA Montlake Market Remediation (PCO 225) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[818] 119_NWR - SR 513 Comm & Htl Offers (PCO 246) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[819] 120_SPU PRS Pipe Conn - Const Only (PCO 244, 253) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[820] 121_Pier 3 Core-Test Reimbursement (PCO 240) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[821] 122_UL Ltg Nighttime Cir - Const (PCO 188) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[822] 123_Additional Camera Relocations (PCO 257) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[823] 124_BCS HMI Location (PCO 256) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[824] 125_Add'l Hotel Offers for ML Proj (PCO 248) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[825] 126_WABS Conduit Supports over 5Ft (PCO 262) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[826] 127_Elim. Environmental Incentive (PCO 268) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[827] 128_Hazardous Bldg Matls Allowance (PCO 269) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[828] 129_Landscape Mods in OCR - Design (PCO 238) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[829] 130_WABS Eqpt Pltfrm Angle Matls (PCO 273) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[830] 131_Strip Seal Replacement (PCO 002) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[831] 132_Relays & Monitoring Points (PCO 176) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[832] 133_DRB Compensation (PCO 278) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[833] 134_Landscape & Urban Des TR Revs (PCO 97, 185) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[834] 135_Express Lanes Sign Cont Wiring (PCO 266) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[835] 136_Underlid Closure Signs (PCO 288) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[836] 137_WABS Shaft Duct Clearing (PCO 284) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[837] 138_Pavt Depth for DXEI Alignment (PCO 285) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[838] 139_Correction to CO 138 (PCO 294) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[839] 140_Ethafoam Requirement (PCO 286) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[840] 141_LWB Long-Term Closure (PCO 292) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[841] 142_Mult Issue Res No. 2-2022 (PCO 182,277,279,290,291,293) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[842] 143_Multiple Issue Res No. 3-2022 (PCO 083,261,265) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[843] 144_Mult Issue Res No. 4-2022 (PCO 237,245,252,270,271,282,295)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[844] 145_Noise Threshold Mods (PCO 283) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[845] 146_WABS Deck Conc Agg Size Mod (PCO 300) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[846] 147_DXEI Ramp Shoulder Pvmt Mod (PCO 302) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[847] 148_Hamlin Alley Permanent Pole (PCO 297) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[848] 149_Balsamo Prop Dmge Claim Stlmt (PCO 307) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[849] 150_Bockus Prop Dmge Claim Stlmt (PCO 311) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[850] 151_Metro Bus Facility Spare Parts (PCO 050) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[851] 152_Subcontractor Percentages (PCO 310) Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[852] 153_MLB & LWB Extended Closures (PCO 309) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[853] 154_HMA Testing Performed by DB (PCO 314) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[854] 155_Strike-WABS Sch Recov and Time (PCO 317) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[855] 156_Lease Transfer Eastlake Office (PCO 315) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[856] 157_Eastlake Office 3rd Flr Rental (PCO 316) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[857] 158_Irrigation Controller Mods (PCO 312) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[858] 159_Additional Interpretive Signs (PCO 327) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[859] 160_LWB Sidewalk Depth (PCO 330) (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[860] 161_Independent RSUP Closure (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[861] 162_Storm Drainage Mods Bet W17&18 (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[862] 163_Truck Apron Mod at MLB & LWB (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[863] 164_Sign Bridges 2 & 3 Sign Mods Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[864] 165_Elim. Ptg of SS Gutters & D-S (Executed)ReviewedIncorporated into conformed RFP through CO 165 062302024
-
[865] 166_Landscape Modifications (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[866] 167_Underlid Luminance Test Sce (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[867] 168_SDOT Cabinet (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[868] 169_Multiple Issue Reso No. 5-2024 (Executed)Reviewed868-001: Install safety platform in Fire Flow Vault prior to Physical Completion
-
[869] 170_Multiple Issue Reso No. 6-2024 (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[870] 171_Multiple Issue Reso No. 7-2024ReviewedNo relevant changes to Completion or handover requirements.
-
[871] 172_WABS ATM VMS Extended Warranty (Executed)Reviewed872-001: Provide 3-year extended warranty for 9 ATM signs
-
[872] 173_Elec Signs Anti-Graffiti Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[873] 174_Transit Canopy Paint (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[874] 175_Topsoil Gradation (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[875] 176_PLB Girder Paint Modification (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[876] 177_City Street Long Term Closure (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[877] 178_Multiple Issue Reso No. 8-2024Reviewed002-209: Revised to reflect updated laptop screen size from 15" to 13" minimum
-
[878] 179_Transit Canopy Paint Spec (Executed)ReviewedNo relevant changes to Completion or handover requirements.
-
[879] 180_Multiple Issue Reso No. 9-2024Reviewedchanges to as-built requirements, not to completion requirements
-
[880] 181_POTUS MotorcadeReviewedNo relevant changes to Completion or handover requirements.
-
[881] 182_Sign Bridge No. 4 ModificationsReviewedNo relevant changes to Completion or handover requirements.
-
[882] 183_VP Candidate MotorcadeReviewedNo relevant changes to Completion or handover requirements.
-
[883] 184_SRP Design ModificationsReviewed002-058: Added SRP deletion notation to as-built plans
-
[884] 185_Multiple Issue Reso No. 10-2025Reviewed002-058: Added cable length variance notations to as-built plans
-
[885] 186_Multiple Issue Reso No. 11-2025Reviewed002-196.9: Supply water treatment materials prior to Substantial Completion
-
[886] 187_SRP Over Ex. Swr. Mod - ConstReviewedNo relevant changes to Completion or handover requirements.
-
[887] 188_Multiple Issue Reso No. 12-2025ReviewedNo relevant changes to Completion or handover requirements.
-
[888] 189_Physical Completion Added CDReviewed001-024: Extended Physical Completion timing from 120 to 244 calendar days